Machine Capacity

Manage and analyze machine scheduling constraints.

Week 22 — 26 May to 31 May 2026
AvailableScheduledOverloadedOffline
Work CenterCapacity
hrs/day
Mon 26Tue 27Wed 28Thu 29Fri 30Sat 31Week LoadAvail.Status
IM-01 — Injection 18.0
8.0h
9.5h ⚠
7.0h
8.0h
10.0h ⚠
4.0h
46.5h40.0hOverloaded
IM-02 — Injection 28.0
6.0h
8.0h
8.0h
5.0h
3.0h
0.0h
30.0h40.0hOK
IM-03 — Injection 38.0
Offline
Offline
Maint.
8.0h
8.0h
4.0h
0.0h20.0hOffline
AS-01 — Assembly 18.0
8.0h
9.0h ⚠
8.0h
7.5h
6.0h
4.0h
42.5h40.0hOverloaded
LP-01 — Logo Printing8.0
5.0h
4.5h
3.0h
5.0h
4.0h
0.0h
21.5h40.0hOK
CR-01 — Crusher4.0
3.5h
2.0h
0.0h
4.0h
2.0h
0.0h
11.5h20.0hOK
Total All Work Centers151.5h160.0h
IM-01overloaded by 6.5h this week (Tue +1.5h, Fri +2.0h)  · AS-01overloaded by 2.5h (Tue +1.0h)  ·  Consider moving PO-0044 Wiper Blade to Wed or splitting across IM-02.