PO Load Analysis

Review specific capacity allocation and load per Production Order.

PO No.ItemQtyWork CenterOperationRequired HrsAvailable HrsVarianceScheduledStatus
PO-0041Floor Broom Blue500IM-01Op 2016.7h16.0h+0.7hMon–TueTight
PO-0041Floor Broom Blue500LP-01Op 308.3h40.0h-31.7hWedOK
PO-0044Wiper Blade Red1,000IM-01Op 2033.3h16.0h+17.3hTue–FriOverloaded
PO-0042Toilet Brush Set300IM-02Op 2010.0h24.0h-14.0hWedOK
PO-0043Mop Head Cotton200AS-01Op 10–2011.0h16.0h-5.0hMon–TueOK
PO-0045Dustpan Set Blue400IM-02Op 2013.3h16.0h-2.7hWedOK
Total This Week92.6h128.0h-35.4h